1 viewer
Wind · CO · being built
Singing Grass Wind
A planning estimate from monthly means and the spread of days inside a month.
- Rated
- 602 MW
- A year
- 1,918 GWh
- Capacity factor
- 36.4%
Before it reports
- Owner
- Public Service Co of Colorado
- Where
- Kit Carson County, CO
- Nameplate
- 603 MW in 1 generator
- Stage
- Under construction, half built or less
- Planned start
- Sep 2027
- Model, a whole year
- 1,918 GWh
- Neither the inventory nor the turbine database names a turbine: taken as 3400 kW on a 140 m rotor at 105 m, the median of the 2447 turbines on land the U.S. Wind Turbine Database dates 2024 or later.
- Capacity, position, stage and start
- EIA-860M inventory of planned generators for September 2026, plant 68982
- Climate
- NASA POWER's monthly climatology at 39.2011, -102.8576
- Read
- 2026-11-11
The site
The plant
- Turbines
- 177
- Wind at the record's height
- 6.53 m/s at 50 m
- Before losses
- 43.5%
- Lost to wakes
- 11.2%
- Fit to run
- 96.0%
- Ground the farm spreads over
- 9,714 ha
| Turbines | Rotor m | Hub m | W per m2 swept | Wind at hub m/s | Rated wind m/s | Capacity factor | A year |
|---|---|---|---|---|---|---|---|
| 177 x 3,400 kW | 140.0 | 105.0 | 221 | 7.25 | 9.5 | 36.4% | 1,918 GWh |
Through the year
| Month | Wind m/s | Air kg/m3 | Before losses | Energy |
|---|---|---|---|---|
| Jan | 6.54 | 1.082 | 44.7% | 167.1 GWh |
| Feb | 6.66 | 1.080 | 45.8% | 154.8 GWh |
| Mar | 7.03 | 1.059 | 48.9% | 182.8 GWh |
| Apr | 7.49 | 1.043 | 52.5% | 190.1 GWh |
| May | 6.68 | 1.023 | 44.8% | 167.7 GWh |
| Jun | 6.36 | 0.999 | 41.1% | 148.9 GWh |
| Jul | 5.73 | 0.989 | 34.2% | 127.8 GWh |
| Aug | 5.71 | 0.996 | 34.1% | 127.5 GWh |
| Sep | 6.30 | 1.011 | 40.8% | 147.6 GWh |
| Oct | 6.64 | 1.040 | 44.8% | 167.6 GWh |
| Nov | 6.70 | 1.064 | 45.9% | 166.0 GWh |
| Dec | 6.60 | 1.083 | 45.3% | 169.4 GWh |
In 3D
To scale: 140 m rotors on 105 m hubs, four diameters apart across the wind and seven along it. Nacelles are drawn by rule. 6 of 177 turbines drawn. 3D starts when Virtual's renderer loads.
What the model leaves out
- The wind is one monthly mean speed with a Weibull spread. Direction, gusts, the daily cycle and terrain are not in it.
- The power curve is a cube to rated power at one power coefficient. A real curve rounds off below rated wind.
- Wakes are a share of output that grows with the turbine count, not a layout worked through.
- Icing, curtailment by the grid operator and noise or wildlife shutdowns are not counted.