One life of this Sedimentary exhalative zinc-lead mine takes 3 steps from 3 raw materials: 0 run here, 3 by partners, 0 are bought. 6 inputs are still opaque.

Figures are estimates from typical published values: grades, recoveries, costs and prices are not measured at any mine, and the orebody is generated from a seed, not surveyed. The page runs 30,000 blocks, and a finer model moves these figures. Nothing here is sent to any machine or partner. Format cre8.mine.make.v1.
Open VirtualWhere the real mines are
On these prices
Does not pay
Net present valueEvery year's cash on the assumed prices, discounted at 8 % a year.
-$62M
Grade
ZN 5.6 %, PB 2.8 %, AG 30 g/t
Milled
6,813,057 t
Rate
2,062 t a day
Life
10.5 years

Run a mine

The ground

Deposit model
31a
In the ground
15,015,512 t
ZN in it
840,869 t
PB in it
420,434 t
AG in it
450 t
Drilled
538 holes, 105,940 m
Drilling
$19M over 392 days

The plan and the run

Method
Sublevel open stoping
Treatment
Crush, grind and float
Planned
7,570,064 t over 3 levels
Cut-off
$55/t
Fleet
2 drill rigs, 3 loaders, 8 trucks
Walked
3,892 days
First ore
day 508
Revenue
$878M
Operating cost
$469M
Plant and development
$318M
Rate of return
3.89 %
Carbon dioxide
27,668 t

Who does the workOwner work a person does is a one-shift work order paid in usd at the assumed wage, in the shape the village paymaster posts. Contract work is paid through the metre rate, and a machine's work is a machine cost. The page posts no order.

On the books at peak
203 people, 40 of them contractors
Machines with no one in the seat
0
Owner wages
$186M
Paid hours
2,460,971 worked, 182,322 breaks, 398,147 leave and training, 184,317 travel and blast window, 675,046 with nothing to do
Work orders drafted
30
The roster
RoleAnswersPosts a shiftPeopleAn hourThe assumed loaded wage for the role, in US dollars.Licence
Mine managerowner11$116mine manager's certificate where the state issues one
Mine engineerowner88$68.8
Geologistowner22$63.5
Surveyorowner22$50.2
Safety and training officerowner11$58.2
Shift bossowner28.84$65.5competent person for workplace examinations
Jumbo operatorcontractor14.42$55
Bolterowner14.42$52.4
Boltercontractor28.84$52.4
Blasterowner14.42$55blaster's certificate
Blastercontractor14.42$55blaster's certificate
Long-hole drillerowner28.84$55
Diamond drillercontractor28.84$55
Loader operatorowner313.3$52.4
Loader operatorcontractor14.42$52.4
Truck drivercontractor14.42$47.1
Service crewowner313.3$44.5
Service crewcontractor28.84$44.5
Crusher operatorowner14.42$47.1
Hoist operatorowner28.84$52.4hoist operator's certificate where the state issues one
Mill operatorowner522.1$49.8
Lab technicianowner14.42$41.9
Paste and fill operatorowner14.42$47.1
Ventilation technicianowner14.42$49.8
Environment technicianowner14.42$47.1
Mechanicowner730.9$57.6
Electricianowner28.84$60.2electrician's licence
Office: safety, stores, people, accountsowner2020$39.7
28 rows
Every task
TaskStepDone byA person is a human or an NPC filling the post. Remote is an operator at a surface console. Robot is a machine on its own, watched from a console, and plant is the plant's own control.RoleAnswersChecked byHoursThe task's hours: a machine's when a machine did it.At the workHours a person spent at the work itself.WhyWhy a person does the task at every level, or how it is paid when it is not a work order.
Mark up the face and linebreakpersonSurveyorownerMine engineer3,2183,218a work order
Map the face geologybreakpersonGeologistownerMine engineer1,6091,609a work order
Drill the development roundbreakpersonJumbo operatorcontractorShift boss8,5808,580contract: paid through the development metre rate
Charge and fire the roundbreakpersonBlastercontractorShift boss10,72510,725A certified blaster charges and fires at every level; charging machines exist, firing stays with a person.
Muck out the headingbreakpersonLoader operatorcontractorShift boss4,2904,290contract: paid through the development metre rate
Truck development rock outbreakpersonTruck drivercontractorShift boss10,72510,725contract: paid through the development metre rate
Scale, bolt and mesh the backbreakpersonBoltercontractorMine engineer21,45121,451A person reads loose ground before anyone works under it; bolting rigs automate the cycle, not that judgement.
Extend air, water, power and vent ductbreakpersonService crewcontractorShift boss16,08816,088contract: paid through the development metre rate
Drill the production ringsbreakpersonLong-hole drillerownerShift boss63,08463,084a work order
Charge and fire the stope or benchbreakpersonBlasterownerShift boss20,43920,439A certified blaster charges and fires at every level; charging machines exist, firing stays with a person.
Load the broken rockbreakpersonLoader operatorownerShift boss116,590116,590a work order
Cable-bolt the stope backs and browsbreakpersonBolterownerMine engineer22,71022,710A person reads loose ground before anyone works under it; bolting rigs automate the cycle, not that judgement.
Diamond-drill the next stopesbreakpersonDiamond drillercontractorGeologist90,84190,841contract: paid through the development metre rate
Survey the stopes and benchesbreakpersonSurveyorownerMine engineer4,5424,542a work order
Sample and call ore from wastebreakpersonGeologistownerMine engineer30,28030,280a work order
Break oversize and run the crusherhoistpersonCrusher operatorownerShift boss85,62485,624a work order
Wind the skipshoistpersonHoist operatorownerMechanic13,74313,743a work order
Ride and tend the cagehoistpersonHoist operatorownerShift boss85,62485,624a work order
Run the millmillpersonMill operatorownerMine engineer328,715328,715a work order
Assay mill and grade-control samplesmillpersonLab technicianownerMine engineer27,25227,252a work order
Balance the metal and tune recoverymillpersonMine engineerownerMine manager27,25227,252a work order
Run the paste plantmillpersonPaste and fill operatorownerMine engineer24,42024,420a work order
Build barricades and watch the pourbreakpersonPaste and fill operatorownerMine engineer19,53619,536a work order
Keep roads, pumps and pipesbreakpersonService crewownerShift boss159,572159,572a work order
Carry explosives, bolts and parts to the workbreakpersonService crewownerShift boss79,78679,786a work order
Survey the air and set vent controlsbreakpersonVentilation technicianownerMine engineer79,78679,786a work order
Watch the tailings dam and watersitepersonEnvironment technicianownerMine engineer85,62485,624a work order
Keep the hoist, mill and fanssitepersonMechanicownerMine engineer159,572159,572a work order
Keep the power and controlssitepersonElectricianownerMine engineer79,78679,786a work order
Examine each working placebreakpersonShift bossownerMine manager6,8686,868A competent person examines each working place every shift before work begins (30 CFR 57.18002, cited from memory).
Design, schedule and check ground controlsitepersonMine engineerownerMine manager120,096120,096a work order
Train and keep the mine rescue teamssitepersonSafety and training officerownerMine manager4,4484,448Two rescue teams of five are drawn from the crews and kept trained (30 CFR 49, cited from memory).
Answer for the mine under its permitsitepersonMine managerownerthe inspector20,01620,016A named person answers for the mine under its permit.
Service and repair the machinesbreakpersonMechanicownerMine engineer173,201173,201a work order
Keep machine electrics and cablesbreakpersonElectricianownerMine engineer37,11537,115a work order
Lead the shiftsitepersonShift bossownerMine manager96,76796,767a work order
Safety, stores, people and accountssitepersonOffice: safety, stores, people, accountsownerMine manager320,996320,996a work order
37 rows

What it takes

Depth
189 m
Air
196.2 m³/s, fan 604.2 kW
Water in
32.2 L/s, pump 85.21 kW
Rock at the bottom
19.7 °C
Diesel
10,323,759 L
Power
203,748,896 kWh
Explosive
4,552,423 kg
Cement
146,517,365 kg
Steel
5,753,312 kg
Reagents
8,925,105 kg
Water
3,297,520 m³

Every tonneWhat came out of the ground went somewhere named: every tonne of rock and of metal is on one of these lines.

The walk closes to
0.00000035 t
Came inTonnesZN tPB tAG t
mineralised rock in place15,015,512840,869420,434450
barren rock broken1,180,243000
development rock828,782000
3 rows
Went toTonnesZN tPB tAG t
left in the ground8,625,691474,485239,185253
left in stopes757,00636,63818,12520
waste dump828,782000
rock fill0000
paste fill3,516,41724,42611,04731
tailings dam2,513,95818,6928,56122
zinc concentrate551,206286,62700
lead concentrate231,4770143,516124
8 rows

What the drilling got wrongThe plan stands on the drill holes and the walk mines the true ground, so the two differ.

Tonnes against plan
1
MetalTrue over plannedMetal in the ground the walk mined, over the metal the plan expected there.Reached the millMetal that arrived at the mill, over the metal the plan expected to send.
ZN0.8660.78
PB0.8820.794
AG0.8740.787
3 rows

How it is made

Sedimentary exhalative zinc-lead ore (raw): 6810000000 kg per Concentrates from one Sedimentary exhalative zinc-lead mine life; mined: Sedimentary exhalative zinc-lead by Sublevel open stoping.Sedimentary exhalativ…Waste rock in place (raw): 829000000 kg per Concentrates from one Sedimentary exhalative zinc-lead mine life; mined: rock broken to reach the ore.Waste rock in placeExplosive (opaque): 4550000 kg per Concentrates from one Sedimentary exhalative zinc-lead mine life; Bought in; its own chain is not followed here..ExplosiveDiesel (opaque): 10300000 L per Concentrates from one Sedimentary exhalative zinc-lead mine life; Bought in; its own chain is not followed here..DieselCement (opaque): 147000000 kg per Concentrates from one Sedimentary exhalative zinc-lead mine life; Bought in; its own chain is not followed here..CementGround support steel (opaque): 644000 kg per Concentrates from one Sedimentary exhalative zinc-lead mine life; Bought in; its own chain is not followed here..Ground support steelBroken rock (material): Drill, blast and load, made by a partner (mining). 1 run per Concentrates from one Sedimentary exhalative zinc-lead mine life; described. Energy: at least 163000000 kWh; 4 opaque inputs carry no energy.Broken rockRock at surface (material): Hoist to surface, made by a partner (mining). 1 run per Concentrates from one Sedimentary exhalative zinc-lead mine life; described. Energy: at least 167000000 kWh; 4 opaque inputs carry no energy.Rock at surfaceGrinding steel (opaque): 5110000 kg per Concentrates from one Sedimentary exhalative zinc-lead mine life; Bought in; its own chain is not followed here..Grinding steelReagents (opaque): 8930000 kg per Concentrates from one Sedimentary exhalative zinc-lead mine life; Bought in; its own chain is not followed here..ReagentsProcess water (raw): 3300000000 kg per Concentrates from one Sedimentary exhalative zinc-lead mine life; drawn: make-up water.Process waterConcentrates from one Sedimentary exhalative zinc-lead mine life (product): Crush, grind and float, made by a partner (mineral_processing). 1 run per Concentrates from one Sedimentary exhalative zinc-lead mine life; described. Energy: at least 308000000 kWh; 6 opaque inputs carry no energy.Concentrates from one…
made hereby a partnerboughtrawrecoveredopaque: make not knownstripe: who is meant to make itnot disclosedwhere buying starts

Walk it in VirtualOpen Virtual from the top of this page, then type these in its console.

Stand in this mine
mine open sedex 7
Read it
mine status

Every raw material

38 materials from 37 kinds of deposit.
MaterialGroupFound inThe kinds of deposit that carry the material. Each opens that mine on this page.Used forMake leafWhere a make graph already asks for the material, the leaf it names.
CopperbasePorphyry copper, Volcanogenic massive sulfide, Sediment-hosted copper, Copper skarn, Polymetallic vein, Komatiitic nickel sulfidewire, motors, circuit boardscopper-ore
ZincbaseVolcanogenic massive sulfide, Sedimentary exhalative zinc-lead, Mississippi Valley zinc-lead, Polymetallic veingalvanising, brass, die castings
LeadbaseVolcanogenic massive sulfide, Sedimentary exhalative zinc-lead, Mississippi Valley zinc-lead, Polymetallic veinbatteries, solder, shielding
NickelbaseNickel laterite, Komatiitic nickel sulfide, Layered intrusion reefstainless steel, battery cathodes
TinbaseTin vein and greisen, Alluvial gold placersolder, tinplatetin-ore
Aluminium (bauxite)baseLaterite bauxiteframes, cable, cans
IronferrousBanded iron, Sedimentary manganesesteeliron-ore
ManganeseferrousSedimentary manganesesteel, battery cathodes
ChromiumferrousLayered intrusion reef, Podiform chromitestainless steel, plating
MolybdenumferrousPorphyry copper, Porphyry molybdenumalloy steel, catalysts
TungstenferrousTungsten skarn, Tin vein and greisencarbide tools, drill bits
VanadiumferrousBanded iron, Layered intrusion reef, Sandstone uraniumhigh-strength steel, flow batteries
TitaniumferrousLayered intrusion reef, Kaolin and common clay, Heavy mineral beach sandswhite pigment, airframes
GoldpreciousPorphyry copper, Volcanogenic massive sulfide, Copper skarn, Polymetallic vein, Orogenic gold vein, Epithermal gold-silver vein, Carbonate-hosted gold, Alluvial gold placercontacts, reserves, jewellery
SilverpreciousPorphyry copper, Volcanogenic massive sulfide, Sedimentary exhalative zinc-lead, Mississippi Valley zinc-lead, Sediment-hosted copper, Copper skarn, Polymetallic vein, Orogenic gold vein, Epithermal gold-silver vein, Carbonate-hosted goldsolder, solar paste, contacts
Platinum grouppreciousKomatiitic nickel sulfide, Layered intrusion reefcatalysts, electrodes
LithiumbatteryLithium pegmatite, Lithium brinebattery cathodes, glass
CobaltbatterySediment-hosted copper, Nickel laterite, Komatiitic nickel sulfidebattery cathodes, superalloys
GraphitebatteryFlake graphitebattery anodes, refractories
Rare earthsbatteryCarbonatite, Heavy mineral beach sandsmagnets, phosphors
UraniumenergySandstone uranium, Marine phosphoritereactor fuel
CoalenergyBituminous coal seamcoke, power, carbon feedcoal
LimestoneconstructionLimestone quarrycement, lime, fluxlimestone
Crushed stoneconstructionCrushed stone quarryconcrete, road base
Sand and gravelconstructionSand and gravel pitconcrete, fill
GypsumconstructionBedded salt and gypsumplaster, cement setting
Common clayconstructionKaolin and common claybrick, cement
Silica sandindustrialSand and gravel pit, Quartz and pegmatite silica, Heavy mineral beach sandsglass, foundry, siliconsilica-sand
High-purity quartzindustrialQuartz and pegmatite silicasilicon, cruciblesquartz
KaolinindustrialKaolin and common clayceramics, paperkaolin
SaltindustrialBedded potash, Bedded salt and gypsumchlorine, soda ash, de-icing
PotashindustrialLithium brine, Bedded potashfertiliser
Phosphate rockindustrialCarbonatite, Marine phosphoritefertiliser, LFP cathodes
SulfurindustrialBedded salt and gypsumsulfuric acid
BoratesindustrialLithium brine, Lacustrine borateglass fibre, detergentscolemanite
FluorsparindustrialMississippi Valley zinc-lead, Carbonatitehydrofluoric acid, flux
BariteindustrialMississippi Valley zinc-lead, Carbonatitedrilling mud, fillers
CelestineindustrialBedded salt and gypsumstrontium salts, pyrotechnicscelestine